Nigeria’s 2026 Mini-Grid Regulations: Licensing, Tariff Compliance, and Investment Protection for Off-Grid Energy Developers.

The Nigerian Electricity Regulatory Commission (“NERC”) issued the Mini-Grid Regulations 2026 (NERC-R-001-2026) pursuant to section 226 of the Electricity Act 2023. The Regulations...


Abstract

The Nigerian Electricity Regulatory Commission (“NERC”) issued the Mini-Grid Regulations 2026 (NERC-R-001-2026) pursuant to section 226 of the Electricity Act 2023. The Regulations update the framework for the development and operation of mini-grids in Nigeria. This article examines the principal legal and commercial implications of the new framework, including the oversight of NERC and State regulators; capacity limits of up to 5 MW for isolated and 10 MW for interconnected mini-grids; registration, permit and site exclusivity requirements; the Mini-Grid Tariff Model under Schedule 14 and its efficiency benchmarks; and the procedures for managing grid arrival. It also considers environmental requirements, customer protection and dispute resolution.

Keywords: NERC Mini-Grid Regulations 2026; Licensing Framework; Tariff Compliance; Off-Grid Energy; Electricity Act 2023; State Electricity Regulation; Site Exclusivity; Investment Protection; Mini-Grid Developers; Environmental Protection.

Introduction

Nigeria continues to face a serious shortage of reliable electricity, particularly in rural and off-grid areas. Extending the national grid to these areas is often expensive and may not be commercially viable. As a result, many communities remain without a steady electricity supply. This has increased the need for other ways of providing electricity, including mini-grids, which can serve communities that the national grid does not adequately reach.

The Nigerian Electricity Regulatory Commission (“NERC”) first introduced rules for mini-grids through the Mini-Grid Regulations 2016, made under the now repealed Electric Power Sector Reform Act 2005 (“EPSRA”). These rules were later replaced by the Mini-Grid Regulations 2023 (NERC-R-117-2023) (“2023 Regulations”), made under section 226 of the Electricity Act 2023 (“EA 2023”), which repealed EPSRA.

While the 2016 and 2023 Regulations supported the growth of mini-grids, they had some limitations. These included restrictions on the size and capacity of mini-grid projects, challenges in attracting investment, and uncertainty about how federal and state electricity regulators would oversee their operations.

The Mini-Grid Regulations 2026 (“2026 Regulations”), made under section 226 of the EA 2023 and published by NERC in April 2026, seek to address these challenges. They provide a more developed framework for mini-grid operations and aim to make mini-grids more commercially attractive, encourage investment, and strengthen their role in the development of Nigeria’s electricity market. Unless stated otherwise, section references are to the 2026 Regulations.

Federal and State Regulatory Oversight

Under the EA 2023, States may regulate electricity within their territories, and several have set up State Electricity Regulatory Commissions (“SERCs”). Where a SERC has assumed oversight of intrastate electricity activities, the 2026 Regulations apply in that State only to matters that remain within NERC’s jurisdiction or are expressly reserved to NERC by law (section 4(5)). A permit holder need not obtain a duplicative permit, approval, study or filing for a purely intrastate project where a materially equivalent one has already been accepted, save for inter-state, national-grid or federal-market matters (section 4(6)). NERC may also rely on approvals and studies accepted by a SERC (section 4(7)).

Expanded Scope and the Licensing Regime

Under the 2023 Regulations, both isolated and interconnected mini-grids were generally limited to an installed capacity of 1 megawatt (MW) per site. The 2026 Regulations increase this limit to 5 MW for isolated mini-grids and 10 MW for interconnected mini-grids (section 4(1)). Developers can now undertake larger projects without moving into the licensing framework for larger electricity businesses. No separate licensing regime applies to mini-grids above 1 MW, and additional requirements for them apply only where expressly stated (section 4(3)–(4)). Larger projects can also serve businesses such as agricultural processing, cold storage and small manufacturing.

For an isolated mini-grid, the project must be located in a designated unserved area and must not materially conflict with the network expansion plan of the relevant Electricity Distribution Company (“DisCo”) approved by NERC (section 7(1)(b)). Where the project area is expressly covered by the DisCo’s approved expansion plan, the developer must obtain the DisCo’s written consent or no-objection. If the DisCo fails to respond within 15 business days, it is deemed to have issued a no-objection (section 7(2)–(3)). Any objection by the DisCo will lapse if physical construction has not begun within 12 months, or if energisation or substantial completion has not occurred within 24 months, unless NERC grants an extension for good cause (section 7(5)). NERC may still grant a permit where the mini-grid better serves timely electrification than the DisCo’s planned expansion (section 7(7)). In addition, the developer must file an agreement with the host community in the form in Schedule 11, or in another form agreed by the parties and accepted by NERC (section 7(1)(e)).

The developer of an isolated mini-grid of up to 100 kilowatts (kW) may choose either to register the project using the form in Schedule 2 or to apply for a full permit (section 8). Registration is simpler, but does not carry the grid-arrival protection given to permit holders (see below). Isolated mini-grids above 100 kW and up to 5 MW must obtain a permit from NERC before commencing operations.

For interconnected mini-grids, which are connected to and operate alongside an existing distribution network, the developer, the DisCo and authorised representatives of the host community must sign a tripartite agreement, which must be filed with NERC (section 9(1)). Interconnected mini-grids of up to 10 MW require both the registration of this agreement and a permit (section 9(2)). DisCos must publish feeder-level Hosting Capacity Information at least every 12 months (section 9(3)). After construction, the DisCo must issue energisation approval, or give written technical reasons for withholding it, within 15 business days (section 9(18)), and disputes on refusal to interconnect go to NERC (section 9(19)).

NERC is expected to decide on a complete permit application, or register a tripartite agreement, within 30 business days (section 10(2)). However, the Regulations do not expressly provide that an application will be automatically approved if NERC fails to respond within that period. There may, however, be an argument under section 4(1) of the Business Facilitation (Miscellaneous Provisions) Act 2022, which provides for deemed approval where a Ministry, Department or Agency fails to communicate its decision within the timeline stated in its published list of requirements.

Developers may also secure a site. A community and the DisCo may grant a developer exclusivity of up to 12 months, extendable by NERC for up to 12 more months (section 25(1)– (2)). Once registered, NERC will not grant a permit for that site to another developer, any competing community agreement is void, and an encroaching developer may be barred for up to 12 months (section 25(7), (10) and (16)). The DisCo, however, retains its right to extend its network (section 25(8)). In addition, a permit or permitted business cannot be transferred or sold without NERC’s prior written consent (section 15(1)), which is relevant to investors planning an acquisition or exit.

Tariff Compliance and Operational Benchmarks

Under the 2023 Regulations, operators could set tariffs using NERC’s Multi-Year Tariff Order (“MYTO”) methodology, with loss limits of 4% (technical) and 3% (non-technical), or by agreement with a community consuming not less than 60% of the output.

The 2026 Regulations replace this approach with a Mini-Grid Tariff Model provided in Schedule 14, which must be used by permit holders to determine retail tariffs and other charges (section 23(1)). A registered operator may still use the Schedule 14 model or agree tariffs with the community, represented by customers consuming not less than 60% of the output (section 23(8)). Such an agreement must be filed with NERC and remains subject to tariff review (section 23(9)–(10)). The tariff control period is 5 years unless NERC approves otherwise (section 23(7)), and a permit holder may file a single tariff application for a portfolio of sites (section 23(6)). This builds on NERC’s earlier adoption of the African Forum for Utility Regulators (“AFUR”) Mini-Grid Tariff Tool for permit applications, with effect from 16 December 2024, under the 2023 Regulations.

MYTO is not removed completely, however. Section 24(14) still refers to MYTO-linked charges between an interconnected mini-grid and the DisCo, such as network use and energy purchase fees, settled under Schedule 8. An interconnected mini-grid of 1 MW or more may also apply to export power, and the DisCo must decide within 30 business days (section 24(8)–(9)).

The 2026 Regulations also retain the default limits of 4% for technical losses and 3% for non-technical losses (section 23(2)). However, unlike the previous Regulations, NERC can now approve higher loss limits for individual projects where justified by the location, line length, customer density, condition of inherited assets, metering status or other features of the project (section 23(3)). Unless NERC approves otherwise for good cause, technical losses may not exceed 8% and non-technical losses may not exceed 5%, and these higher allowances must be reduced over a period not exceeding 36 months from the commercial operation date, or such other period as NERC approves (section 23(5)).

Investment Protection and Grid Arrival Safeguards

The 2026 Regulations introduce clearer rules on what happens when the national grid reaches an area already served by an isolated mini-grid. Under the 2023 Regulations, after 12 months’ written notice from the DisCo, the operator could either convert to an interconnected mini-grid or transfer its distribution assets to the DisCo for compensation.

The 2026 Regulations retain the 12-month notice requirement (section 21(2)) but provide more options for the permit holder. These include converting the project into an interconnected mini-grid, transferring its assets to the DisCo or another approved operator, continuing to operate under a service, franchise or other commercial arrangement agreed by the parties and approved by NERC, orderly decommissioning under an approved plan, or any other arrangement approved by NERC (section 21(3)). If the parties do not agree within 60 business days, either party may refer the matter to NERC (section 21(4)).

Under the 2023 Regulations, compensation was mainly based on the depreciated value of the distribution assets and an amount linked to the pre-tax profit earned by the operator in the 24 months before the transfer. The 2026 Regulations introduce a new measure called the Compensable Transfer Value. This is the higher of the verified indexed historical cost of the assets, net of depreciation and excluded contributions, and the verified net depreciated replacement cost of the assets. Approved handover, removal and decommissioning costs are also recoverable (section 21(5)(a)–(b)).

The additional compensation an operator may receive depends on how long the mini-grid has been in commercial operation before the grid arrives. Where the grid arrives within the first five years, the operator may recover its unrecovered development and construction costs, together with an amount equal to the revenue generated in the 12 months before the transfer. Between five and ten years, it receives an amount equal to the revenue of the preceding 12 months. After ten years, compensation is generally limited to the value of the assets, unless NERC finds that exceptional unrecovered prudent capital remains (section 21(5)(c)). NERC may direct payment as a lump sum within the agreed period or 30 days of approval, failing which interest accrues, or in time-bound instalments (section 21(8)–(9)). Importantly, the permit holder may continue operating until the transition arrangement is approved and compensation is paid or legally secured (section 21(10)).

Compensation excludes speculative future profits and expenses that were not prudent or efficiently incurred (section 21(5)(e)). These protections apply to permit holders only. Where the grid reaches a registered mini-grid, the operator must, on the DisCo’s request and subject to NERC’s direction, decommission and remove its assets or enter into another approved arrangement (section 21(12)).

Overall, these changes give permit holders clearer options and a more predictable basis for recovering their investments, which gives investors and lenders greater confidence.

Environmental Protection and Compliance

The 2026 Regulations retain the requirement for mini-grid operators and permit holders to comply with all applicable environmental laws, permits and directives of the competent environmental authority (section 19(1)). However, requirements now depend on the type of project and its environmental risk.

Under this approach, solar photovoltaic and battery-supported mini-grids of up to 10 MW require evidence of environmental screening and an Environmental and Social Management Plan (“ESMP”), and a full Environmental and Social Impact Assessment (“ESIA”) is not required solely because of their capacity. Where the competent environmental authority requires a different pathway for a specific project, the developer shall request written reasons based on site-specific environmental or social circumstances (section 19(2)). However, a full ESIA is required for projects involving hydro, biomass or thermal generation, resettlement or material land-use impact, sensitive areas such as forest reserves and wetlands, or where the environmental authority requires one (section 19(3)).

Permit holders must also implement waste management, battery handling, health and safety, fire safety, spill prevention and community grievance procedures (section 19(4)). Importantly, a mini-grid cannot commence commercial operation until the developer has provided NERC with evidence of compliance with the applicable environmental pathway (section 19(5)). This reduces the time and cost of lower-risk projects without reducing environmental protection.

Customer Protection, Compliance and Dispute Resolution

Permit holders must give customers, before connection, a customer service charter covering billing, meter failure, complaints, outages and service restoration (section 17(2)–(3)). They must also use the standard connection agreements in Schedule 12, and the Metering Code applies to all mini-grids unless NERC grants a derogation (section 20(1) and (3)). NERC may also inspect a permit holder’s audited accounts and adjust tariffs (sections 13–14). NERC may serve a notice to rectify a breach, and non-compliance attracts sanctions (section 26). Disputes under the Regulations must first be negotiated for 30 days, after which they go to NERC for final adjudication (section 29).

Practical Points for Developers and Investors

Developers should confirm early whether NERC or a SERC has jurisdiction, check the DisCo’s expansion plans and hosting capacity data, and register exclusivity over promising sites. For small isolated projects, the choice between registration and a permit should be made with grid arrival in mind. Investors should note that tariffs may be reviewed and that any transfer of a permitted business requires NERC’s consent.

Conclusion

The Mini-Grid Regulations 2026 provide a detailed commercial framework for Nigeria’s off-grid energy sector. By increasing capacity limits, clarifying the roles of NERC and State regulators, setting out a clearer approval process, protecting development sites, establishing tariff rules and providing a process for dealing with grid arrival, the Regulations address several of the risks that have affected mini-grid development. They also provide a more specific environmental pathway for solar PV and battery-supported projects, while preserving the need for a full assessment where the law or the circumstances of a project require one. The impact of these rules will depend on how consistently NERC and State regulators apply them, and how well developers and distribution companies comply with their obligations. For developers and investors, understanding the approval requirements, tariff rules and asset-transfer process will be important when deciding whether a mini-grid project is commercially viable.